Warragul aged care hydronic replacement

Building owner, direct engagement

Contract value
$1,420,000
Duration
11 months
Sector
Health
Systems
Mechanical, Hydraulic, Maintenance
Completed
2021
Chiller and pump skid viewed from the plant room floor

Brief

Replacement of end of life boiler plant, hydronic heating and heated water services to a 96 bed residential aged care facility across three wings.

Systems installed

  • 3 × 400kW condensing gas boilers in N+1, cascade controlled on return water temperature
  • 2 × 1,200 litre calorifiers with thermostatic mixing to 45°C at resident outlets, AS 4032.3
  • 1,850m of pre-insulated hydronic reticulation to 96 rooms and four common areas
  • Primary and secondary variable speed pumps, 2 × 11kW duty/standby on each circuit
  • Water safety plan and Legionella control regime to AS/NZS 3666.3, with monthly sampling points
Insulated hydronic pipework packed into a shallow ceiling void

Constraints

Residents were not relocated for any part of the works. Heating was maintained to every occupied room by running the existing boilers on a temporary header while the new plant was built alongside, then cutting over one wing at a time across three weekends. The changeover window was fixed by the heating season and closed on 1 May, after which the old boilers could no longer be relied on to carry a wing.

Outcome

Cut over across three weekends in October and November 2021 with no room off heating for more than six hours. Site gas consumption metered at 31% below the previous year over the following winter on comparable degree days. Facility rolled onto a scheduled maintenance contract in December 2021.